Name
Baev Oleg Andreevich
Scholastic degree
—
Academic rank
—
Honorary rank
—
Organization, job position
Russian Scientific-Research Institute of Land Improvement Problems
Web site url
—
Articles count: 2
This article gives estimation of drying (liquidation)
ponds with subsequent selection of the most optimal
variant. For example, ponds â„– 1, 2 have the
calculations for the four drainage options: bottom
outlet, using a mobile diesel pumping stations,
through the siphon outlet, as well as the combined
option of draining (via a bottom outlet and mobile
pumping stations). The results of the calculation for
each of the cases were examined; the article
summarizes the estimated parameters, which allow to
visualize and choose the most optimal variant of
drying, depending on the time of evacuation
The article presents the design study for construction
of a drainage system on the territory of gardening
association «Zarya» in the region of Gukovo in
Krasnosulinsky district of Rostov region.
Construction of a drainage system is a prerequisite
for reducing the groundwater level caused by the
infiltration of the drainage complex mine called
Burgustinskaya. The results of the calculations
determined the value of the total infiltration
groundwater feeding; inflow rate to each of the 6
drains per unit length, water flow ability of a
horizontal pipe drainage, as well as a diameter of
drainage pipes